JOPLIN, Mo. — What one person called, “A Christmas miracle” in an online comment, is really a Thanksgiving miracle!

The South Rangeline overpass of the Kansas City Southern Railroad was open to all traffic Wednesday, November 23 at 11:52 a.m.

Range Line Bridge Replacement Fact Sheet_4

The project completes early. 23 days early.

The estimated completion was Dec 16. However good weather for construction and priority planning by MoDOT officials achieved the early opening.

MoDOT inspectors tell us on site there are still things to complete outside of the roadway, cosmetic issues like sod and dirt work.

Final inspections were completed in the past week. Painters were spotted on the bridge yesterday and this morning as tipsters alerted us that the opening could be close.

Now accessible is the newly relocated Maria’s Restaurant, in the former Pacific Rim building, across from Import Warehouse.

This is a breaking news story, stay with Joplin News First on KOAM News Now as we continue to cover news and important stories where you live. Scroll below and sign up for our JLNews email list so you don’t miss an article.

FOLLOW OUR SOCIALS, SEE NEWS WHILE YOU SURF…

 

View this profile on Instagram

 

Joplin News First (@joplinnewsfirst) • Instagram photos and videos

 

Leave a Reply

Your email address will not be published. Required fields are marked *